EPCI OF BELUM AND PEMANIS SUBSTRUCTURES

The scope of this projects cover Engineering Design, Procurement, Construction, Transportation and Installation (EPCI) of Belum and Pemanis Substructures for SK-309/SK-311 PHASE 2 GAS DEVELOPMENT PROJECT

CLIENT : MURPHY SARAWAK OIL CO LTD
LETTER OF AWARD : 30 SEPTEMBER 2010

MECHANICAL COMPLETED DATE :
15 FEBRUARY 2011 (BELUM)
15 MARCH 2011 (PEMANIS)

TURNOVER DATE:
28 FEBRUARY 2011 (BELUM)
28 MARCH 2011 (PEMANIS)

OFFSHORE MECHANICAL COMPLETED DATE:
31 MARCH 2011 (BELUM)
30 APRIL 2011 (PEMANIS)