Baram Compression and Production Platform BAKP-B Module 2 & 3, Module Support Frame (MSF) and Flare Boom
Client : PETRONAS CARIGALI Award Date : 12 October 2004 Completion Date : 11 September (MSF & Flare Boom) : 11 October 2005 ( M2 & M3) Tonnage : 3,100MT
The contract encompassed the fabrication of total 3,100 metric tonnes of Baram Compression and Production Platform BAKP-B Module 2 & 3, Module Support Frame (MSF) and Flare Boom.
Module 2 is the Crude Production Module with processing facilities. Module 3 is the Power Generation Module incorporating the Gas Turbine Generator, Power Plant Sub-station, Uninterrupted Power System and 16-man shelter. Both modules will be installed on the MSF at its offshore location.
Upon completion, the facilities will be installed at the Baram South oil field located approximately 25km from Baram Shoreline with oil production expected in late Quarter 4, 2005.
Project by: Oil and Gas Unit
Last updated: 16/07/2008